In order to meet the requirements for commissioning and provide theowner with (including but not limited to)the following training content,the owner's personnel must organize technicians and operators whomeet the requirements of chemical production technology and skills oneyear before the completion of the machinery to participate in thefollowing training work and pass the assessment,which is crucial forsubsequent trial production and completion acceptance.Operators donot have a year of theoretical learning and about half a year of practicaltraining and examination can not reach the operational ability.
Contact Us
Commissioning Services for Propane Dehydrogenation and Related Projects
It is applied in the synthesis of methane-rich gas with hydrocarbon (Light oil, naphtha, LPG, light hydrocarbon, hydrocarbon-containing dry gas etc.) and steam as raw materials. The resulted gas can be further used to produce hydrogen, syngas with different CO/H2 ratio (for the synthesis of methanol or ammonia etc.) and coal gas.
Product Details
(1) Preparation of pre-construction data
The plant engineers prepare various production materials in accordancewith the Sinopec test management guidelines,including participating indesign review and related activities,and providing correspondingtraining services to the owners.This work must be started one and a halfyears before the completion of the machine to prepare for the owner'spersonnel training.Complete(including but not limited to)the followingstarting materials:Basic theoretical knowledge of each device process,basic knowledge of equipment and instruments,operation proceduresof each device,operation method of each device position,accidenthandling plan of the device,plant test plan,linkage test plan,feedingtest plan,accident list of similar devices,SIS interlocking logic manual,PSSR preparation before starting,individual operation manual of eachdevice,device purge plan,Device airtight scheme,device drying scheme,oven scheme,loading scheme,device opening and stopping scheme,etc.The process is expected to take a year and a half.
(2) Pre-start training
(3) Technical support during design phase
(4) Pre-test the main work
(5) The main work of the test phase
(6) Operation, performance assessment (PT) and delivery acceptance (TO) main work
After the end of driving, the device enters the stage of improving the production load and product quality and testing the safety and stability performance of long cycle operation. Comprehensively guide the construction unit to gradually increase the system load, improve the production capacity of the device, reduce product consumption, optimize the process operation index, test the long-term operation of various safety facilities, find and rectify the existing problems, in order to achieve the safe and stable operation of the device, high quality and high yield of the product, the best process index, the quantitative operation and adjustment of the site environment, the maximum economic benefits. Until the performance conditions promised by the patent vendor are met.
Operation conditions
Catalyst Characteristics